Before resetting, you can try the following:

  • Clean the gate opener, control unit and photocells, including the inside. A common cause is spider webs, dirt on the photocell covers, etc.
  • Disengage the gate and manually check for any mechanical obstructions. An obstruction can also appear some time after installation, for example due to a change in temperature.
  • If you suspect a fault with the photocells, disconnect them and test the gate opener without them.
 

Resetting the MCU1 and MCU4 control units (NICE Robus RBS 400/600/600HS gate opener)

Note: This procedure only erases the control unit's memory; the remote controls will remain stored in it.
Resetting:

  1. Press and hold the first (Open) and third (Close) buttons simultaneously
  2. When all the LEDs light up, release the buttons
  3. Wait for the control unit to reset

Recognising the connected gate-opener devices

Each time you connect, disconnect or change the wiring of accessories on the BlueBUS inputs and STOP the accessory recognition procedure must be performed accessory recognition phase. The gate opener will alert you that this operation is required by flashing LEDs L1 and L2.

Recognising connected devices on the NICE Robus RBS400, RBS600 and RBS600HS gate opener
  1. Press the “Open” and “Stop/Set” buttons and hold them
  2. As soon as L1 and L2start flashing rapidly, release the buttons
  3. Wait a few seconds for the control unit (MCU1 or MCU4) to complete the device recognition process.
  4. If everything went smoothly, the STOP LED should be lit and L1 and L2 should go out. Alternatively, L3 and L4may start flashing if you have not yet completed the gate leaf length recognition phase.

Recognising the gate leaf length

For the gate to move correctly (specifically, to calculate its acceleration and deceleration distances and partial opening), the gate opener must determine the length of the gate leaf itself. During this operation, the gate opener moves the gate from one end stop to the other and uses a switch to determine the gate length.

Recognising the sliding gate leaf length using a NICE Robus RBS400, RBS600 or RBS600HS gate opener
  1. Press the “Close” and “Stop/Set” buttons and hold them
  2. Release the buttons as soon as the gate starts moving
  3. The opening cycle should start; if it does not, press the “Stop/Set” button and check the gate's direction-of-travel setting (see Selecting the gate's direction of travel) and start again from step 1.
  4. Otherwise, if the gate opens in the correct direction, wait for the gate opener to complete the opening and then closing cycle.

Programming the gate opener

For complete gate-opener programming instructions, see Programming the gate opener with an MCU1 control unit or MCU4.

Resetting the RBA3 control unit (NICE Robus 400/600/1000 and RUN1500 gate opener)

Note: This procedure only erases the control unit's memory; the remote controls will remain stored in it.
Resetting:

  1. Press and hold the first (Open) and third (Close) buttons simultaneously
  2. When all the LEDs light up, release the buttons
  3. Wait for the control unit to reset

Recognising the connected gate-opener devices

Each time you connect, disconnect or change the wiring of accessories on the BlueBUS inputs and STOP the accessory recognition procedure must be performed accessory recognition phase. The gate opener will alert you that this operation is required by flashing LEDs L1 and L2.

Recognising connected devices on the NICE Robus RB600 gate opener
  1. Press the “Open” and “Stop/Set” buttons and hold them
  2. As soon as L1 and L2start flashing rapidly, release the buttons
  3. Wait a few seconds for the control unit to complete the device recognition process.
  4. If everything went smoothly, the STOP LED should be lit and L1 and L2 should go out. Alternatively, L3 and L4, unless you have not yet completed the gate leaf length measurement phase.

Measuring the gate leaf length

For the gate to operate correctly (specifically, to calculate the acceleration and deceleration distances and partial opening), the operator must determine the gate leaf length itself. During this operation, the operator moves the gate from one stop to the other and uses a switch to determine the gate's length.

Measuring the sliding gate leaf length using a NICE Robus RB600 operator
  1. Press the buttons “Close” and “Stop/Set” and hold them
  2. Release the buttons as soon as the movement sequence begins
  3. The opening sequence should begin. If it does not, press the “Stop/Set” button and check the gate's travel direction setting (see Selecting the gate's travel direction) and start again from step 1.
  4. Otherwise, if the gate opens in the correct direction, wait for the operator to complete the opening and subsequent closing sequence.

Programming the operator

For complete operator programming instructions, see Programming the operator with the RBA3 control unit

 

Resetting the RBA4/A and RBA4 control units (NICE Road 200/400 operator)

Note: This procedure only erases the control unit's memory; the remote controls stored in it will remain.
Resetting:

  1. Press and hold the first (Open or Radio) and third (Close or P.P.) buttons simultaneously
  2. Release them when all the LEDs light up
  3. Wait for the control unit to reset

Setting up the operator again:
For detailed instructions, see: fortamigo.ie/na-posuvnu-branu/pohon-pre-posuvne-brany-do-400-kg-nice-road-rd400

Measuring the gate leaf length

For the gate to operate correctly (specifically, to calculate the acceleration and deceleration distances and partial opening), the operator must determine the gate leaf length itself. During this operation, the operator moves the gate from one stop to the other and uses a switch to determine the gate's length.

Measuring the sliding gate leaf length using a NICE Road RD400 operator
  1. Press and hold the second (Stop/Set) and third (Close or P.P.) buttons simultaneously
  2. Release the buttons as soon as the movement sequence begins
  3. The opening sequence should begin. If it does not, press the second button (Stop/Set) and check the gate's travel direction setting (see Selecting the gate's travel direction) and start again from step 1.
  4. Otherwise, if the gate opens in the correct direction, wait for the operator to complete the opening and subsequent closing sequence.

Programming the operator

For complete operator programming instructions, see Programming the operator with the RBA4 control unit

Resetting without photocells

If you suspect that the photocells are not working correctly, disconnect them and on the control unit bridge inputs 1 and 5 (applies only to the Road operator with the RBA4 control unit). This closes the photocell circuit, allowing you to test that the operator is working correctly without the photocells.  

 

Resetting the MC424L control unit (NICE Wingo 2024/3524 operator)

Note: This procedure only erases the control unit's memory; the remote controls stored in it will remain.
Resetting:

  1. Disconnect the control unit from the mains (or remove the F1 power fuse) and wait for all the LEDs to go out.
  2. Press and hold buttons P1 and P2 on the control unit (the control unit should still be disconnected from the power supply)
  3. While holding buttons P1 and P2, reconnect the control unit to the mains (or reinsert the power fuse)
  4. Release the buttons after exactly 3 seconds (i.e. during the third second)
  5. If the erase procedure was successful, all the LEDs will go out for one second. If this does not happen and the LEDs continue flashing, repeat the erase procedure from the beginning

To check that the memory has been erased correctly, disconnect the control unit from the mains (or remove the F1 power fuse) and wait for all the LEDs to go out. When you reconnect it to the mains, all the LEDs should flash for about six seconds if the memory has been completely erased. If the LEDs flash for only three seconds, the erase procedure probably failed and must be repeated.

Setting up the operator again: For detailed instructions, see: fortamigo.ie/na-posuvnu-branu/nice-moon-mc424-riadiaca-centrala-pre-24v-pohony-kridlovych-bran-rodiny-wingo

Measuring gate leaf travel

For the gate to operate correctly (specifically, to calculate the acceleration and deceleration distances and partial opening), the control unit must determine the gate leaf opening arc length itself. During this operation, the operators move the gates from one stop to the other and determine the gate opening interval length. 

Note: If you have already completed the gate leaf travel measurement phase, you must, before measuring again, erase the control unit's memory.

Before measuring gate leaf travel, check that the devices connected to the inputs STOP, PHOTO and are working correctly and connected properly. are working correctly and connected properly. If any of them is activated during the measurement, the process must be repeated. Ideally, the gate leaves should be about halfway open. To do this, release the operators and manually move the leaves to a half-open position, then engage the operators again. After engaging the motor, always move the leaf slightly by hand so the motor engages. In principle, however, the position of the leaves before measurement does not matter.

The gate leaf travel measurement procedure is automatic and proceeds as follows:

  1. Press the P2 button
  2. Both leaves open slightly
  3. The secondary (lower) leaf closes
  4. The primary (upper) leaf closes
  5. The primary (upper) leaf opens
  6. After the programmed secondary motor delay the secondary (lower) leaf begins to open. If the delay is unsuitable, press the P2 button and set a suitable delay
  7. The control unit measures the travel required to open the gate fully (i.e. until it reaches the mechanical stops)
  8. Both leaves close fully. The leaves begin closing at different times to prevent them from rubbing against each other as they close
  9. The control unit saves the measured values, and that's DONE.

All the phases listed above must run one after another without any intervention from you. If any phase does not proceed correctly, stop it by pressing the P1 button and, if necessary, adjust the settings and repeat the process.

Programming the operator control unit

For complete control unit programming instructions, see Programming the MC424L control unit

 

Resetting the MC424LR10 control unit (NICE Wingo 2024/3524 operator)

Note: This procedure only erases the control unit's memory; the remote controls stored in it will remain.
Resetting:

  1. Press and hold the first (OPEN) and third (CLOSE) buttons simultaneously
  2. When all the LEDs L1..L8 start flashing (after approx. 3-4 seconds), release them
  3. Wait 5 seconds; the control unit will then be restored to factory settings.

Initial setup of the control unit (or measurement after a reset)

  1. Set/check the drive model selector switches according to table 2.6 in the control unit manual
    Note: i.e. WG2024 motor: 1-down, 2-up, 3-down, 4-down; WG3524: 1-up, 2-up, 3-down, 4-down; TOO3024: 1-down, 2-up, 3-up, 4-down; TOO4524: 1-up, 2-up, 3-up, 4-down; SFAB2024: 1-down, 2-down, 3-down, 4-up; unspecified model: 1-up, 2-down, 3-down, 4-down
  2. Manually release the gate leaves and move them to the halfway position (open to approx. 45°), re-engage the operators, then pull the leaves slightly so the motors engage
  3. On the control unit, press and hold the second (STOP/SET) and third (CLOSE) buttons simultaneously. Release them when the leaves start moving
  4. The leaves will perform the following sequence (movement detection can be interrupted at any time by pressing the STOP button)
    1. Both leaves open slightly
      Note: If they move in the opposite direction—that is, if they close slightly—you will need to interrupt the operation by pressing the STOP button, disconnect the control unit from the power supply, and reverse the polarity on both motors. If one leaf starts opening and the other starts closing, reverse the polarity only on the motor that started closing. To reverse the polarity, swap the wires between the + (plus) and − (minus) terminals in that motor's three-terminal motor connector.
    2. The lower leaf closes fully
      Note: If the wrong leaf (that is, the upper one) starts moving, interrupt the operation by pressing the STOP button, disconnect the control unit from the power supply, and swap the complete M1 and M2 motor terminal blocks.
    3. The upper leaf closes fully
    4. The upper leaf starts opening, followed shortly by the lower leaf
      Note: If the delay is too short, you can change it in the programming settings; see section 5.2.2, LED L6 “Leaf delay”.
    5. Both leaves open fully
    6. The lower leaf starts closing, followed shortly by the upper leaf
    7. The leaves close fully, and the control unit stores their end positions in memory
    8. Done

Programming the gate operator control unit

For complete instructions on programming the control unit, go to Programming the MC424LR10 control unit

Resetting the ROA40R10 control unit (NICE Rox ROX600 and ROX1000 operator)

Go to Instructions for resetting the NICE Rox operator.