NICE HOPP HO7124 has a built-in control unit POA3R10. This articulated-arm operator can operate a single gate leaf on its own. For a double-leaf gate, a second motor is connected to it HO7224 without a control unit; the unit in the HO7124 then controls both operators.
The motor runs on 24 V DC. The operator is non-backdrivable; in the event of a power failure, unlock it with the key. The built-in control unit is mains-powered at 230 V AC.
What to add to the HOPP operator
Choose the equipment based on the entire gate and the risks in its surroundings. Electronic accessories connect to the control unit in the HO7124; the HO7224 has no inputs or receiver socket of its own.
| What | Why | Type |
|---|---|---|
| Second motor | For the second leaf; controlled by the POA3R10 unit built into the HO7124. | |
| Photocells | Monitor the passageway; two-wire connection BlueBUS. | |
| Warning light | Signals movement; connects to FLASH. | |
| Remote control | The receiver fits in the HO7124. The kits listed include this receiver and one two-channel remote control. | |
| Code/keypad or card access control | Compatible control devices connect to BlueBUS. | |
| Backup battery | In the event of a mains failure, it powers the system via the POA3R10 in the HO7124; the number of movements depends on the gate and the battery charge. | |
| External manual release | Enables manual release in the event of a power failure when there is no other entrance to the property. |
|
| Service and diagnostics | The programmer connects to the POA3R10 via the BUS T4 interface. |
When to choose NICE HOPP
HOPP is an articulated-arm operator with an aluminium arm for swing gates that open inwards onto the property. It is also suitable for more intensive use, provided the gate meets the mechanical and operating limits. These operators are not suitable for gates that open outwards.
| Length of one gate leaf | Weight of one gate leaf |
|---|---|
| Up to 1.5 m | Up to 250 kg |
| Up to 2.4 m | Up to 160 kg |
The maximum values of 2.4 m and 250 kg do not apply simultaneously. For lengths between these values, follow the permissible-load curve. Two motors operate two leaves; they do not increase the load capacity of a single leaf. Solid infill, wind, friction, and the condition of the hinges affect suitability and service life.
Load and estimated service life
To estimate the service life, add the relevant indices. Read the result from the original chart. This is an approximate estimate assuming regular maintenance, not a guarantee of the number of cycles.
| Effect and index | Service life chart |
|---|---|
At a shared interval boundary, use the higher index for an approximate assessment. The service life result does not replace checking the permitted length and weight or testing the force on the completed gate.
Kits for one or two leaves
One leaf: HO7124 with control unit. Two leaves: HO7124 with control unit and HO7224 without control unit. Both motors are controlled by the control unit in the HO7124. All the kits listed below include OXIBD and 1× ON2E. The version with photocells includes one pair of EPMB; the version with accessories also includes a flashing light ELDC.
| Kits for 1 leaf | Second motor HO7224 without control unit | Kits for 2 leaves |
|---|---|---|
HOPP for 1 leaf![]() Basic With photocells With accessories 1× HO7124 Control unit in the HO7124. The limit applies to one leaf. | NICE HO7224![]() 24 V DC The HO7224 has no control unit; it is controlled by the unit in the HO7124. | HOPP for 2 leaves![]() Basic With photocells With accessories HO7124 + HO7224 Control unit in the HO7124. The limit applies to one leaf. |
Installing the operator and articulated arm
Before installation, check that the gate is sturdy, the leaf is balanced, and it moves smoothly by hand throughout its full travel. The operator does not replace repair of damaged hinges. Attach the arm bracket to a solid part of the leaf, such as the frame. The anchoring surface must safely withstand the forces exerted by the operator.
| What to check | Requirement |
|---|---|
| Motor location | Minimum installation width 170 mm; the operator body is 180 mm wide. Check the full outline and arm reach. |
| Clearance for arm movement | Maintain at least 400 mm at the location shown in the drawing. This is not the post cross-section dimension. |
| A/B geometry | It depends on the hinge position and the required opening angle; refer to the chart below. |
| Access | Safe access to the release key and cover must remain available. |
| Obstacles and pedestrian gate | The leaf or arm must not hit a wall or other object. For an integrated pedestrian gate, the operator must be disabled while it is open. |
How to determine installation distances A and B
- Measure the distance A based on the hinge position and mounting surface shown in the drawing.
- Open the leaf by hand to the required position and determine its angle.
- Use the value of A and the required angle range on the chart to determine B, that is, the position of the motor bracket. Dimensions are in millimetres.
Manufacturer’s example: for A = 100 mm and an angle of 100°, B is approximately 180 mm. This example is not a universal installation dimension.
The chart distinguishes the ranges 90–95°, 95–100°, 100–105° and 105–110°. A larger angle is not possible with every hinge offset; both A and B must remain within the applicable range.
| Dimension A | Dimension B |
|---|---|
![]() | ![]() |
Anchoring the brackets and assembling the arm
- Hold the motor bracket level and mark the four holes. Choose anchor bolts, washers, and wall plugs according to the substrate; these fixing components are not included.
- Attach the motor to the bracket using the two supplied M4.8 × 13 screws.
- Connect the curved arm to the straight arm using the pin and retaining ring. Attach the gate-leaf bracket in the same way.
- Release the motor and, with the gate closed, determine the position of the gate-leaf bracket. Extend the arms as shown in the original drawing and position the bracket as far from the operator as possible.
- Attach the bracket horizontally to the rigid frame of the gate leaf. Reconnect the joint using the pin and retaining ring; then check the full travel and set the stops.
Adjusting the mechanical stops
The motor has mechanical stops with fine adjustment for opening and closing. The stops set the end positions for subsequent programming.
- Release the motor with the key and manually move the gate leaf to the desired open position.
- Turn plastic disc A on the underside until the cut-out is positioned beneath the arm, as shown in the drawing.
- Insert stop B in the first available position, oriented correctly. Turn the disc to secure it and prevent it from falling out.
- Fine-tune the position using screw C. If the closing stop is not on the ground, set the closing stop in the motor in the same way.
- Tighten the disc's retaining nut D to prevent it from turning on its own. Manually check that both positions are reached, then lock the motor again.
| Position of disc A | Fine adjustment C and locking D |
|---|---|
![]() | ![]() |
Preparing the wiring
Cables must be suitable for the installation location. Route cable entries so that water or condensation cannot run into the electronics. Prepare the mains supply, grounding, and power isolation according to the specific installation.
| Wiring | Cable and length |
|---|---|
| 1 – Supply to HO7124 | 3 × 1.5 mm², up to 30 m. For longer runs, the manufacturer specifies 3 × 2.5 mm² and grounding at the automation system; verify the supply cable is suitable for the specific installation. |
| 2 – Flashing light | 2 × 1 mm², up to 20 m. |
| 3 – Antenna | RG58 coaxial cable, up to 20 m; recommended length less than 5 m. |
| 4 – BlueBUS | 2 × 0.5 mm², up to 20 m; for 20–40 m, use 2 × 1 mm². |
| 5 – Key switch | Two 2 × 0.5 mm² cables or one 4 × 0.5 mm² cable, up to 50 m. |
| 6 – Electric lock | 2 × 1 mm², up to 6 m. |
| 7 – Interconnecting the operators | 3 × 1.5 mm², up to 10 m; follow the terminal block and original wiring diagram. |
HOPP control unit and wiring
HO7124 has a built-in POA3R10 and a mains supply of 230 V AC. The motors in the set operate at 24 V DC. HO7224 must not be connected directly to 230 V.
The following wiring and setup instructions apply to the POA3R10. This board is not interchangeable with the older POA3. For repairs, check the label on the board actually installed and its connectors; a similar operator name is not enough.
Disconnect both the mains supply and backup battery before opening the cover.
POA3R10 terminals
| Terminal | Use |
|---|---|
| M1 | Output for HO7224 without a control unit. |
| M2 | Output for HO7124 motor with control unit. With a single motor unit, HO7124 remains connected. |
| FLASH | ELDC flashing light or 12 V DC bulb-type flashing light, maximum 21 W. |
| EL | 12 V AC electric lock, maximum 15 VA. |
| BlueBUS | Power and communication for compatible devices via two non-polarized wires. Maximum 12 BlueBUS units; the load is calculated according to the types of devices connected. |
| STOP | Safety input for an NO, NC, or 8.2 kΩ resistive device; the type is learned during device setup. |
| SbS | Voltage-free NO contact for step-by-step control. |
| OPEN | Voltage-free NO contact for partial opening; the function can be changed by programming. |
| Receiver antenna | Coaxial cable to the antenna connector actually fitted on the OXIBD receiver; follow the labels on its terminals. |
Do not apply an external voltage to the SbS and OPEN control inputs. Changing the function of FLASH or EL also changes the electrical characteristics of the output: for other auxiliary functions, it is intended for a 24 V DC lamp or relay, maximum 4 W. Do not use a load rated for the original function without checking first.
Auxiliary power on the POA3R10
For a compatible reader or key-switch lighting, use the right terminal of the STOP pair = − and the left terminal of the SbS pair = +, with the image below oriented so the labels are above the terminals: 24 V DC (−30% to +50%), maximum 200 mA. This pair remains powered in Stand-by mode. Connect the device's command relay separately as a voltage-free NO contact; do not apply an external voltage to the command input. BlueBUS and voltage-free contacts have no +/− polarity. The EL output is 12 V AC/maximum 15 VA with no fixed +/− polarity; FLASH for the flashing light is 12 V DC/maximum 21 W. For a polarized flashing light, check the markings on the board and the light.
BlueBUS photocells and STOP input
EPMB, EDSB and ETPB are connected in parallel to BlueBUS. The TX and RX units of each pair of photocells must have the same jumper settings; each additional pair must have a different address. Set the addresses of the keypads and readers according to their respective instructions. After adding or removing a device, repeat device detection and a functional test.
| Photocell address | HOPP response according to position |
|---|---|
| FOTO / FOTO II | External photocells: when closing, they stop movement and the leaves reopen. |
| FOTO 1 / FOTO 1 II | Internal photocells: when closing, they stop and reverse movement. When opening, they stop the leaves; once the beam is clear, opening resumes. |
| FOTO 2 / FOTO 2 II | Internal photocells: when opening, they stop and reverse movement. |
| FOTO 3 | This configuration is not supported by the HOPP control unit. |
EPMB jumper address table shows the TX/RX settings. The general photocell instructions also include configurations for other control units; for HOPP, use a supported address from the table above.
Standard relay photocells are not a substitute for BlueBUS photocells. For STOP, connect NO contacts in parallel and NC contacts in series. Wire combinations of contacts or multiple resistive safety edges according to the diagrams for the relevant devices; do not disable the safety input by bridging it.
Receiver and remote controls
Insert the receiver into the socket on the HO7124 with the power disconnected. Verified HOPP kits use OXIBD with ON2E. Pairing and deleting remote controls must be carried out according to the receiver actually installed. OXIBD instructions and setup are available on its own page; resetting the POA3R10 does not erase the radio memory.
PS124 backup power supply
For the POA3R10, the PS124 is installed in the HO7124. Connect it only after installation and programming are complete, as it can move the gate even when mains power is off. It must be disconnected when working on the wiring. The battery in the HO7124 also provides backup power to the HO7224 connected to this unit.
The PS124 is not included in the basic kits listed above. After charging, test a full cycle both on mains power and on battery power alone. Speed and the number of operating cycles depend on the battery condition and gate load. Do not assume that a battery connector from another generation is interchangeable.
First start-up and gate test
The arms of all installed operators must be fitted, the stops securely set, and the motors locked. Set the leaves approximately halfway along their travel so they have room to move in both directions during the test. For a two-leaf gate, check the sequence according to how the leaves overlap; they must not collide when closing.
After power-up, the BlueBUS LED should flash regularly once per second, the photocell LEDs should indicate operation, and the FLASH beacon should be off. If the status is incorrect, disconnect the power and check the wiring.
1. BlueBUS and STOP device detection
- Press and hold Open ▲ + Stop/Set.
- After about 3 seconds, when L1 and L2 flash rapidly, release the buttons.
- Wait for the process to finish. The STOP LED should be on and L1/L2 should be off; L3/L4 may start flashing if the positions have not yet been learned.
This learning procedure is also required when no devices are connected. Repeat it whenever BlueBUS or STOP devices are changed; it does not replace learning the gate-leaf travel.
2. Automatic stop-position learning
- After successful device detection, press and hold Stop/Set + Close ▼.
- After about 3 seconds, when L3 and L4 flash rapidly, release the buttons.
- For a two-leaf gate, the sequence is: close M1, close M2, open both motors to the stops, then quickly close both. With a single operator, only the connected motor is learned.
- At the end of a successful closing cycle, L3 and L4 go out.
The first movement must be closing. If a motor opens or the wrong leaf moves first, stop the process using the Open or Close button. With the power disconnected, correct the motor direction or assignment according to the actual wiring, then repeat the learning procedure. Do not mix up the motor and sensor wires.
If a photocell or STOP device is triggered, learning is interrupted and L1 flashes. First remove the cause, then repeat the learning procedure. The force must be appropriate for the gate; increasing it does not compensate for friction or replace a safety test.
Manual and mixed learning for a two-leaf gate
Manual learning lets you set the positions and the delay between overlapping leaves independently. Press and hold Stop/Set + Close, then release as soon as L1 starts flashing, after about 1 second. Press and hold Open or Close to move the corresponding motor; release the button at the desired position. Save the position by pressing and holding Stop/Set for at least 3 seconds. The selected LED lights up, then the next one is selected when you release the button. Allow no more than 10 seconds between actions.
| LED | Position saved for two motors |
|---|---|
| L1 | M1 closing – position 0. |
| L2 | M2 closing – position 0. |
| L3 | SA of motor M2 – the point at which M1 starts opening. |
| L4 | SC of motor M1 – the point at which M2 starts closing. |
| L5 | M1 opening – position 1. |
| L6 | M2 opening – position 1. |
Mixed learning requires a successful automatic learning procedure beforehand. Then enter manual mode, briefly press Open/Close to select the required SA or SC position, and adjust it using the same procedure. Do not change the closed and open positions set by the mechanical stops this way. The manual sequence in the table is for two motors; use automatic learning with a single motor.
Checks before regular use
- Run several complete opening and closing cycles, checking for points of increased friction, arm collisions, and contact between the leaves.
- Correct slowdown, leaf sequence, and reliable end positions.
- Check the operation of each pair of photocells and the STOP device in the relevant directions of movement.
- Manual release, re-engagement, and any backup power supply.
- Measure impact force and protect all crushing, trapping, and entrapment points.
Obstacle detection in the operator does not replace the required safety devices or force measurement.
Programming the POA3R10
Open ▲ and Close ▼ control movement and LED selection. Stop/Set stops movement and is used to enter, change, and save settings. The values below apply to the POA3R10.
Level I – switching functions on and off
- Press and hold Stop/Set until L1 starts flashing, then release it.
- Briefly press Open or Close to select the function LED.
- Use a short press of Stop/Set to change the status: short flashes = OFF, long flashes = ON.
- If no button is pressed for 10 seconds, programming ends and the changes are saved.
The default status of this control board’s functions is OFF. During normal operation, the corresponding LED being lit indicates that the function is enabled.
| LED – function and meaning | Status |
|---|---|
| L1 – Automatic closing ON: after opening, the gate closes after the set pause; the default pause is 30 s. OFF: semi-automatic operation. | OFF – factory setting ON – enabled |
| L2 – Close after photocell activation ON: when automatic closing is enabled, activation of FOTO/FOTO1 during movement reduces the pause to 5 s. If automatic closing is not enabled, activation during closing triggers closing after the set pause. OFF: the original setting applies. | OFF – factory setting ON – enabled |
| L3 – Always close ON: after power is restored, if the gate is detected as not closed, closing starts after a 5 s warning flash. OFF: when mains power returns, the gate remains in place. | OFF – factory setting ON – enabled |
| L4 – Standby all ON: 1 minute after movement ends, BlueBUS, Bus T4, FLASH, EL and some circuits/LEDs are switched off. A command restores operation. OFF: this power-saving mode is not used. | OFF – factory setting ON – enabled |
| L5 – Electric lock / courtesy light ON: EL functions as a courtesy light. OFF: EL controls the electric lock. The load must be suitable for the selected function. | OFF – factory setting ON – enabled |
| L6 – Pre-flashing ON: the warning light flashes for 3 s before movement. OFF: it flashes from the start of movement. | OFF – factory setting ON – enabled |
| L7 – SbS = Open, OPEN = Close ON: the inputs function as Open and Close. OFF: step-by-step and partial opening 1. | OFF – factory setting ON – enabled |
| L8 – FLASH / open gate indicator ON: FLASH indicates that the gate is open. OFF: it functions as a warning light. When changing this setting, use the correct electrical load. | OFF – factory setting ON – enabled |
Level II – parameter values
- Hold Stop/Set until L1 flashes, then release it. Use Open/Close to select the parameter’s input LED.
- Press and hold Stop/Set again; after about 3 seconds, the LED for the current value lights up.
- While continuing to hold Stop/Set, use Open/Close to select the value LED.
- Release Stop/Set. The mode exits if no button is pressed for 10 seconds.
The default value is shown in bold. The input LED identifies the parameter; the LED in the right-hand column identifies its value.
| Input LED – name and description | Setting LED – value |
|---|---|
| L1 – Pause time Waiting time before closing; effective only when automatic closing is enabled. | L1: 5 s L2: 15 s L3: 30 s L4: 45 s L5: 60 s L6: 80 s L7: 120 s L8: 180 s |
| L2 – Step-by-step operation Changes the sequence of commands for SbS and the first radio channel. Values L4/L5/L7/L8 also change the behaviour of Open/Close. | L1: Open – stop – close – stop L2: Open – stop – close – open L3: Open – close – open – close L4: Condominium mode: SbS/Open commands are ignored while opening; Close reverses movement. SbS/Open commands open the gate while it is closing; Close is ignored. A command held for more than 2 s while opening triggers STOP. L5: Condominium mode 2: directional behaviour as for L4; a command held for more than 2 s triggers STOP even while closing. L6: Step-by-step 2: a command held for less than 2 s triggers partial opening. L7: Hold-to-run: movement continues only while the command is held. L8: Semi-automatic opening; closing requires the command to be held. |
| L3 – Motor speed Normal operating speed; always check that forces and deceleration are safe. | L1: Very slow L2: Slow L3: Medium L4: Fast L5: Very fast L6: Fastest L7: Fast opening, slow closing L8: Fastest opening, medium-speed closing |
| L4 – Release after closing Briefly reversing both motors limits the final pressure. | L1: No release L2: Level 1 – approx. 100 ms L3: Level 2 L4: Level 3 L5: Level 4 L6: Level 5 L7: Level 6 L8: Level 7 – approx. 1 s |
| L5 – Motor force Force of both motors. Do not increase it to compensate for a mechanical fault; check impact forces after changing the setting. | L1: Level 1 – minimum L2: Level 2 L3: Level 3 L4: Level 4 L5: Level 5 L6: Level 6 L7: Level 7 L8: Level 8 – maximum |
| L6 – Pedestrian / partial opening When both leaves open together, the smaller of the M1/M2 angles is used. | L1: M2 to ¼ opening L2: M2 to ½ opening L3: M2 to ¾ opening L4: Full opening of M2 L5: Both leaves to ¼ of the smaller angle L6: Both leaves to ½ of the smaller angle L7: Both leaves to ¾ of the smaller angle L8: Both leaves to the full smaller angle |
| L7 – Service reminder Number of manoeuvres before the service reminder; the service indicator must be configured via OVIEW. | L1: 500 L2: 1 000 L3: 1 500 L4: 2 500 L5: 5 000 L6: 10 000 L7: 15 000 L8: 20 000 |
| L8 – Anomaly history Display of the last eight manoeuvres; this is for diagnostic purposes. | L1: Result of the last manoeuvre L2: Result of the 2nd manoeuvre L3: Result of the 3rd manoeuvre L4: Result of the 4th manoeuvre L5: Result of the 5th manoeuvre L6: Result of the 6th manoeuvre L7: Result of the 7th manoeuvre L8: Result of the 8th manoeuvre |
The manufacturer does not specify exact times for the release steps between the end values. Do not calculate them by dividing the range evenly.
POA3R10 diagnostics and reset
In the event of a fault, the warning light emits a short series of flashes, pauses for 1 s, and repeats the same series. The number of flashes helps identify the cause.
| Flashes | Cause | What to check |
|---|---|---|
| 1 | BlueBUS mismatch | Check the devices and wiring. After an actual change to the setup, repeat device learning. |
| 2 | Photocell triggered | Remove the obstruction, clean and align the photocells; check their addresses and operation. |
| 3 | Increased resistance / force limit | Check the gate, hinges, arms and stops. Force adjustment should be changed only after the mechanical cause has been eliminated. |
| 4 | STOP triggered | Check the device and wiring for the STOP. |
| 5 | Internal parameter error | Wait at least 30 s and repeat the command; if the error persists, arrange for servicing. |
| 6 | Permitted load exceeded | Let the operator rest for a few minutes and assess the number of manoeuvres and the friction. |
| 7 | Electrical circuit error | Disconnect all power sources, including the battery, and restore power after a few seconds. If the error recurs, arrange for servicing. |
| 8 | Command continuously active | Check the switch, timer control and SbS/OPEN inputs. |
| 9 | Automation locked | Cancel the lock command using the appropriate control. This does not necessarily mean that the mechanism has been manually released with a key. |
Basic LED check
| LED | Meaning |
|---|---|
| BlueBUS | One flash per second: normal operation. Two quick flashes: input change. Off: check the power supply and fuses; continuously lit: fault. |
| STOP | Lit when the resting state has been correctly learned; turns off when triggered. |
| SbS / OPEN | Lit when the corresponding command is active. |
| L1/L2 flashing | Check and learn the devices. |
| L3/L4 flashing | The limit-stop positions must be learned. |
How to read the fault history
Use Stop/Set to enter programming, then select input L8. Press and hold Stop/Set; after approximately 3 s, the LEDs for manoeuvres with anomalies will light up (L1 = most recent, L8 = eighth). While still holding Stop/Set, select the Open/Close manoeuvre. Its LED will flash the number of times indicated in the fault table. Then release Stop/Set.
Clearing the control unit settings
The reset deletes the custom POA3R10 settings. With the gate stationary, press and hold Open ▲ + Close ▼, until L1 to L8 light up after approximately 3 s. Release the buttons. If the settings are successfully cleared, L1 to L8 flash rapidly for 3 s. Then repeat device learning, position learning and the safety tests. This reset does not clear the receiver's radio memory.
Manual release during a power failure
Release only when the gate leaf is stationary. Insert the key into the release mechanism and turn it 180° in the direction marked on the mechanism. You can open or close the leaf manually without forcing it. Before restoring automatic operation, lock the operator again with the key and remove the key; on a double-leaf gate, check both motors.
Release from the outside
If there is no other access to the property, you can add KIO with cable KA1. For a double-leaf gate, the manufacturer recommends connecting it to the motor for the leaf that opens first from the closed position. The cable is installed in the release mechanism; it does not change the gate's opening direction.
Maintenance and safe use
Schedule servicing no later than 6 months or 20,000 manoeuvres, whichever comes first. Disconnect the mains supply and battery before carrying out any work. Check the anchoring, corrosion, pins and retaining rings, and the condition of the arms, hinges, cables, stops and release mechanism. Repeat the functional and safety tests after carrying out any work.
Do not operate the leaf while anyone is working in its path. Children must not use the gate as a toy, and the controls must be kept out of their reach. If a safety device fails, use the manual release and arrange for repairs; do not disable the safety feature.
NICE HO7124 technical specifications
| Parameter | Value |
|---|---|
| Type | Articulated electromechanical operator, 24 V DC motor. |
| Control unit | Built-in POA3R10. |
| Product power supply | 230 V AC ±10%, 50/60 Hz. |
| Maximum torque | 250 Nm. |
| Rated torque | 100 Nm. |
| Speed at rated torque | 0.13 rad/s (1.2 rpm). |
| No-load speed | 0.17 rad/s (1.6 rpm); adjustable via the control unit. |
| Duty cycle at rated torque | Up to 35 cycles/h; up to 25 cycles/h at the maximum temperature. |
| Continuous operation | Up to 10 minutes; up to 8 minutes at the maximum temperature. |
| Power consumption at rated torque | 170 W. |
| Maximum power consumption | 280 W. |
| Rated current | 0.8 A. |
| Maximum current | 1.3 A. |
| Operating temperature | −20 to +55 °C; performance decreases at low temperatures. |
| Ingress protection rating | IP54 with the cover intact and properly closed. |
| Body dimensions | 180 × 252 × 290 mm (width × depth × height). |
| Operator weight | 9 kg. |
Parameters at rated load apply to ambient conditions of approximately 20 °C. The number of cycles depends on the gate leaf and resistance to movement; the length and weight limits.
360°:
How can I order this item?
Choose the option that suits you:
- order online: use the buy button to add the goods to your shopping cart (you will find the buy button here in the product variants table).
- order by email: place your order at [email protected]